Project Status

Built

Year Completed

2014

Size

43,090 sq. feet

Construction Cost

$6,500,000

Consultants

  • General Contractor: Conlon Construction
  • Mechanical Engineer: Design Engineers
  • Civil Engineer: WHKS
  • Other: C & C Consultants




View all (14) images

Project Description

FROM THE ARCHITECTS:

For many rural communities, the school and its activities are the heartbeat of the community. The significance of this relationship is amplified for this high school which is located in the largest geographic school district in Iowa (555 square miles). With the addition of new administrative, gymnasium, and music spaces, this project strengthens the relationship between the school and its community.

The new program elements are located adjacent to similar existing functions to support the school’s existing organization. They unify the school’s primary façade and update a building that had seen many additions over the past four decades.

A deliberate use of clear and translucent exterior materials creates a visual dialogue between the school’s activities and the surrounding town. Daytime functions in the gymnasium become an extension of the park it faces. Clear glazing in the sunken gym connects students to the exterior at street level. In other areas the glazing is combined with translucent polycarbonate panels to create a pleasant naturally lit learning environment. At night, as music and sports activities begin, the glazing becomes a beacon to the town – and those passing on the highway – as the building emits a soft glow announcing the activities within.
Advertisement
Add a Project
Publish Your Projects Show off and upload images, text, and video of your work. We pick the very best for our project newsletters. Upload

Join the Discussion

Please read our Content Guidelines before posting

Close X