Achieving net-zero energy usage is laudable in any building, but to do it in a nearly century-old building—and one listed on the National Register of Historic Places at that—is exceptional. In Grand Junction, Colo., the U.S. General Services Administration (GSA) and a design/build partnership between Westlake Reed Leskosky and The Beck Group aim to do just that. 

Named for a longtime Colorado congressman, the Wayne N. Aspinall Federal Building and U.S. Courthouse is a three-story, 42,000-square-foot neoclassical structure that has been in continuous use since its construction. The building was first built as a post office and courthouse, and then was expanded in 1939. In the decades since, however, the building had become cramped and outdated, with some alterations such as dropped ceilings obscuring historic features. 

Because the building is listed on the National Register, the project underwent a federally mandated review of its impacts on the building’s historic features, as required under Section 106 of the National Historic Preservation Act. The design team assigned a series of “preservation zones” to the building that helped determine which elements should be retained and which could be disturbed. The most public areas, such as the exterior and lobby, were afforded the most protection. The areas that had the least important historic fabric, such as a nonpublic area in the basement, were given more leeway. 

New interventions included a roof-canopy-mounted, 123-kilowatt photovoltaic array (which generates enough electricity on site to power 15 average homes); the addition of spray foam and rigid insulation to the building shell; the installation of storm windows with solar control film inside the historic windows, in order to preserve the exterior appearance; a 32-well geothermal exchange system for heating and cooling; fluorescent and LED lighting upgrades; and post-occupancy monitoring capabilities. Because the original fenestration needed to be retained, the design team increased daylighting through other means, two examples being a skylight that was installed over a tenant space on the first floor and perimeter ceiling zones that were kept free of building services on the second and third floors.

In some cases, inefficient features, such as the building's original and outdated plumbing fixtures, were replaced. Previously, the building had toilets that used more than 3.5 gallons of water with each flush. The design team researched methods to retain the existing fixtures with new flush valves, but ultimately decided that the best option would be to install low-flow fixtures such as toilets that used only 1.28 gallons per flush.

Finally, one of the most important features of the newly remodeled building may be those that support "passive survivability" in case of a power outage or major emergency—a concept that has emerged in recent years in response to the threat of terror attacks or natural disasters like Superstorm Sandy. These features include natural daylight in the most regularly occupied spaces, a high level of thermal mass and new wall insulation to stabilize internal temperatures, and the ability to use the basement as a shelter in a crisis. 

"This project demonstrated the high value of investment in fairly 'low-tech' measures such as envelope upgrades to dramatically increase energy efficiency," says Paul Westlake Jr., FAIA, managing principal and lead architectural designer for Westlake Reed Leskosky. By choosing durable and efficient materials and fixtures, and respecting the existing structure, the design team has ensured that the Aspinall building could still be around well into another century. 

Click here to see all of the 2014 AIA COTE Top Ten Green Projects. Scroll down for more images, along with performance data and project team and materials information. Stay tuned for profiles of this year's winning firms on Ecobuildingpulse.com, along with additional coverage of this year's Top Ten in the Spring issue of ECOBUILDING Review.

BY THE NUMBERS
Project completion date:
February 2013
Building gross floor area: 41,562 square feet
Estimated percent of occupants using public transit, cycling, or walking: 20
Daylighting at levels that allow lights to be off during daylight hours: 50
Lighting power density (watts per square foot): 0.33
Percent of views to the outdoors: 92
Percent of spaces within 15 feet of an operable window: 0
Percent reduction of regulated potable water: 40
Potable water used for irrigation: No
Total EUI (kBtu per square foot per year): 14
Net EUI (kBtu per square foot per year): 0
Percent reduction from national median EUI for building type: 78
Third-party rating: LEED Platinum
Total project cost as time of completion (land excluded): $15 million

GREEN TEAM
Client, owner: U. S. General Services Administration Rocky Mountain Region—Susan Damour, Rocky Mountain regional administrator; Jason S. Sielcken, project manager; Kenya Freeman, contracting officer—gsa.gov/r8
Design architect, building engineers of record, interior designer/specifications, integrated engineering, mechanical engineer, structural engineer, electrical engineer, technology designer, lighting designer, sustainable designer, and historic preservation consultant: Westlake Reed Leskosky—Paul E. Westlake, Jr., FAIA, managing principal, principal-in-charge, lead architectural designer, and historic preservation expert; Roger Chang, Assoc. AIA, principal, director of sustainability, lead mechanical engineer, high performance green building consultant; Stephanie Banfield, associate, structural design engineer, lead structural designer; Fonda Hosta, associate principal, interior designer; Ruth Albertelli, associate principal, director of specifications, specification writer; Christopher Wilson, mechanical engineer, sustainable design; Carmen J. Mazzant, associate, electrical engineer; Raymond E. Heintel, associate, information technology, technology—www.wrldesign.com
Design-builder, architect of record: The Beck Group—Todd A. Berry, project executive; Michael Murray, AIA, principal-in-charge, Louis Sierra, AIA, project leader—beckgroup.com
Civil engineer: Del-Mont Consultants—James Roberts, vice president—delmont.com
Blast consultant: Weidlinger Associates — Timothy J. Beach — wai.com
Fire protection: Protection Engineering Group—Thomas W. Gardner, principal—pegrouppc.com
Construction manager: Jacobs Technology—Janet Goodman, project executive; Michael Hogan, AIA, design project manager; Dana Squires, construction manager—jacobs.com
Commissioning agent: ME Group—Ravi Maniktala, principal; Carrie Nordby, project manager—megroup.com
MATERIALS
Adhesives, coatings and sealants: Tandus, tandus.com; Shaw Contract Group, shawcontractgroup.com; Forbo, forboflooringna.com; VPI, vpicorp.com; Mohawk, mohawkgroup.com
Building management systems and services: Honeywell, honeywell.co;m Siemens, siemens.com
Carpet: Shaw Contract Group, shawcontractgroup.com; Tandus, tandus.com; Lees, leescarpet.com
Ceilings: Armstrong, armstong.com
Cladding: Dal-Tile, daltile.com
Fabrics: Phifer Inc., phifer.com
Flooring: Forbo, forboflooringna.com; VPI, vpicorp.com; Mannington, mannington.com; Roppe, roppe.com; Johnsonite, johnsonite.com; Design Surface Distributers, designsurfacedist.com; Stone Peak, stonepeakceramics.com
Glass: 3M, 3m.com; Oldcastle Building Envelope, oldcastlebe.com
HVAC: Mitsubishi, mitsubishipro.com; Addison, addison-hvac.com; Armstrong, armstrongpumps.com; United Metal Products, unitedmetal.com; Recold, spxcooling.com; Rittling, rittling.com; Williams, williamsapplied.com; Nailor, nailor.com
Insulation: Lapolla, lapolla.com; Knauf, knaufinsulation.com; Johns Manville, jm.com; Certaintted, certainteed.com
Interior walls: American Gypsum, americangypsum.com; Cemco, cemcosteel.com; Pacific Bulletproof, pacificbulletproof.com
Lighting control systems: EnOcean, enocean.com; NLight, nlight.net
Lighting: Focal Point, focalpointlights.com; Lithonia Lighting, lithonia.com; Sun Valley, usaltg.com; G Lighting, glighting.com
Masonry, concrete and stone: Whitewater Building Material, acsol.net/~whiteh2o; Holcim Cement, holcim.us
Metal: Western Slope Iron, wsiron.com; Brown & Strauss Steel, brown-strauss.com; TrussBilt, trussbilt.com; Kane Sterling, kanesterling.com; Berridge Metal Roofing, berridge.com
Millwork: Nevamar, nevamar.com; Lamin-Art, laminart.com; WilsonArt, wilsonart.com 
Paints and finishes: Sherwin Williams, sherwin-williams.com
Photovoltaics: Sunpower, sunpowercorp.com; DPW Solar, dpwsolar.com; Silverback Solar, silverbacksolar.com; Eaton, eaton.com
Plumbing and water systems: Kohler, kohler.com; Sloan, sloanvalve.com; Zurn, zurn.com; Chicago Faucets, chicagofaucets.com; Halsey Taylor, halseytaylor.com; EEmax, eemaxinc.com; Acorn Engineering, acorneng.com
Renewable energy systems (excluding photovoltaics):Armstrong, armstrongpumps.com; Recold, spxcooling.com; Centennial Plastics, centennialplastics.com
Roofing: Carlisle Roofing, carlisle.com
Structural systems:Boise Cascade, bc.com  
Windows and doors: Schlage, schlage.com; LCN, lcn.com; Von Duprin, vonduprin.com; Oregon Door, oregondoor.com; US Bulletproofing, usbulletproofing.com
Data provided by AIA and Westlake Reed Leskosky.